关于罗宾斯公司设备制造履约情况的公示
Qinling tunnel TBM construction section south line is a critical section for the YHJW project overall schedule controlling, the progress of this section impacts the whole YHJW project schedule. According to the contract of < ON THE SUPPLY OF FULL FACE OPEN TYPE HARD ROCK TUNNEL BORING MACHINE (TBM) FOR YHJW SOUTH LINE PROJECT> requirement, in order to review TBM manufacture schedule, Shaanxi YHJW project construction Co., Ltd, CRTG, Robbins and relative parties had second design review liaison meeting (or second design meeting for short) on December 9th to 10th of 2013. In this meeting the main schedule of south line TBM manufacture was confirmed.
目前,岭南TBM设备制造进度整体滞后(详见附表),严重影响岭南TBM工程的进度。望中铁隧道集团有限公司引起重视,采取合理有效措施,严格履行合同,积极敦促设备制造单位加快岭南TBM设备的制造,保证按期完成合同目标。
Currently, south line TBM manufacture progress is delayed, which is seriously and negatively impacting south line project schedule. Hope CRTG can pay enough attention to this, take proper measures, fulfill the contractual obligations, actively expedite TBM manufacturer speed up TBM manufacturing to achieve the contractual goals.
附表:岭南TBM设备主要部件制造到场时间对比表
Appendix table: south line TBM main components delivery time comparison.
官方抖音
官方微信
官方头条
陕西省引汉济渭 Copyright © 2014 Hanjiang - to - Weihe
River Water Diversion Project Construction Co.Ltd.,Shaanxi Province. 陕ICP备14000942号-1
陕公网安备 61019702000262号